Block Work

0
30
As a QC engineer during the site visit following Non-Conformance observed in block work and issued to the site team now site team need to close out the nonconformance’s prior to further work at the locations.

Which involves the physical rectification of block-wall along with document confirming that a training has been provided to the masons and the same issue will not be repeated in future.

When multiple minors NCR issued for the same issue then this can be considered a “systemic failure.” it will affect the reputation of the subcontractor which can terminate their contract with us.

1. Cavity wall tie not provided as per specification

2. Joints are not uniform and are not properly filled.

3. Scrabbling not done properly at the column.

1. Cavity wall tie not provided as per specification
2. Joints are not uniform & are not properly filled.
3. Lines are not leveled properly.
4. Scrabbling not done properly at the column.
1. Plaster Metal Lath to be fixed all around the joint.
1. Curing of lintel not being monitored.

2. Mortar for block work to be kept properly and out of direct sunlight to reduce water loss.

3. Block to be stored properly to avoid damage.