Prior to Backfilling

0
95
Back-filling around the structure is going to start, as a QC Engineer I will send the following comments to site team and ask for their actions prior to backfilling.
1. Tie rod holes to be filled.
2. The structure below ground level to be protected.(C-4 Paint and Polyethylene sheet)
3. Waste concrete, Binding Wire, Nails, Wooden Ply, Polythene etc to be removed.
Tie rod holes to be filled and structure to be protected.
Waste concrete, Binding Wire, Nails, Wooden Ply, Polythene etc to be removed.
The structure below ground level to be protected.(C-4 Paint and Polyethylene sheet).
The structure below ground level to be protected.(C-4 Paint and Polyethylene sheet).
The structure below ground level to be protected.(C-4 Paint and Polyethylene sheet).